NR/L2/TEL/30028

Installation of Operational Telecommunications Equipment (formerly NR/SP/TEL/30028)

Issue 3, 6 March 2010 · Design process, assurance & records

What the spec is for: minimum requirements for managing installation of operational telecoms equipment (supports NR/L1/TEL/30029)

Clause map — what each clause deals with

1PurposeWhat the spec is for: minimum requirements for managing installation of operational telecoms equipment (supports NR/L1/TEL/30029)
2ScopeApplies to all installation work on operational telecoms equipment on NR infrastructure
3DefinitionsDefinitions — engineering details, like-for-like and so on
4Control of Installation WorkControlling installation work — applies to new and like-for-like
4.1Competency RequirementsCompetency needed to plan and carry out installation work
4.2Risk Identification and MitigationIdentifying and mitigating installation risks
4.3ProceduresMethods of work and workmanship standards
4.4Supervision and AuditSupervision, quality checks and audit
4.5TestingNothing new or replaced (systems, equipment, wiring) is brought into service or connected to working telecoms until testing is finished, where safety could be affected
4.6Adoption of Best PracticeAdopting best practice
5Installation PracticesInstallation practices — general
5.1Transport, Handling and StorageTransport, handling and storage of equipment
5.2Integrity of New EquipmentChecking new equipment is correct and defect-free
5.3Protection of Installed EquipmentProtecting installed equipment from hazards
5.4Tools and Measuring DevicesTools and calibrated measuring devices
6.1Integrity of Existing InfrastructureInstallation work must not disturb existing working telecoms or other infrastructure (live cables, live circuits, walkways, earth bonds) unless safety measures are in place; includes dealing with defective existing wiring
6.2Identification of EquipmentLabelling and identifying new equipment and wiring as installed
6.3SecuritySecurity of equipment and premises during works
7Additional Requirements for New WorkExtra requirements for new work
7.1Application of Engineering DetailsInstalling to the engineering details (the design)
7.2Records of ProgressKeeping progress records
7.3Interface with Testing ActivitiesInterface between installation and testing
8Additional Requirements for Like for Like ReplacementExtra requirements for like-for-like replacement
8.1Use of Infrastructure RecordsUsing infrastructure records when disconnecting/reconnecting
8.2Minor ChangesPermitted minor changes during like-for-like work
8.3Identification of Equipment and Wiring to be DisconnectedIdentifying equipment and wiring to be disconnected

Standards this one points to